INSTALLATION OF SIGNAL POLES AND LIGHTS TO BEGIN
Upcoming change in intersection traffic management. OC Public Works will be replacing existing "STOP" signs with new traffic signal system.
WHAT:
Completed activities:
- Underground utility work and installation of new fiber optic conduit (OC Public Works’ Traffic Management Center remote monitoring system).
- Asphalt/concrete restoration; curb ramp upgrades.
Upcoming activities:
- March 11—15, 2024: Minor utility work
- March 15—early May, 2024: Installation of traffic signal pole foundations, poles, signal lights and associated equipment; Painting of road striping and installation of traffic signs. Traffic signal lights expected to begin operating as early as April 2024.
Attention: Be prepared for temporary closures!
- Intermittent lane closures to accommodate installation of traffic signal poles, signal lights and equipment.
- Temporary sidewalk closures are expected in the project area, yet sidewalks will re-open daily at the conclusion of work. Please use other available sidewalk during closures.
- Access will remain open to/from adjacent residential communities.
- Please observe all project safety signs and barriers when traveling near project work areas.
WHEN:
Early March - Early May 2024
The construction schedule is tentative and subject to change.
Working Days/Hours:
Monday – Friday, 7 a.m. to 3:30 p.m.