This project has been completed
Placement of up to 20,000 cubic yards of sand material from the Santa Ana River, from OC Public Works, at Capistrano Beach within the City of Dana Point. This is a joint project between OC Parks and OC Public Works. Public access may be limited during construction.
What:
• Transport of 20,000 cubic yards of clean sand removed from flood control maintenance in the Santa Ana River.
• Screening of sand and trucking to the beach area north of Palisades Drive.
• Placement of sand along a 550 linear-foot stretch at the north reach of Capistrano Beach.
DETOURS AND SAFETY
Flaggers will direct both pedestrians and bicyclists to avoid the work area. Watch for additional traffic control measures including construction signage.
BACKGROUND
Additional sand serves to counter coastal erosion, protect coastal resources and enhance recreation areas. The California Coastal Commission (CCC) has approved placement of sand as an interim measure.
When:
Anticipated Construction Duration:
July 8 – September 2024
Working Days/Hours:
Monday – Friday, 7 a.m. to 5 p.m.
Working hours and schedule will vary due to tides, inclement weather, ocean conditions and other factors.
Where:
Capistrano Beach Park
35005 Beach Road, Dana Point, CA 92624
Contact Information:
(714) 973-6865
ocparks@ocparks.com