Communications Archive

August 25, 2016 
Camino Del Rio Extension Phase of La Pata Extension Project Begins

News ImageOC Public Works launches work to extend the existing Camino Del Rio roadway in San Clemente's Forster Ranch community to the newly connected La Pata.


July 26, 2016 
La Pata Gap Connector Ribbon Cutting Celebration Update

News ImageOC Supervisor Lisa Bartlett and OC Public Works with Inside the Outdoors Foundation cordially invite you to the La Pata Gap Connector Ribbon Cutting Celebration! Please see the updated flyer with event map attached.


July 7, 2016 
La Pata Gap Connector Ribbon Cutting and Celebration

News ImageOC Supervisor Lisa Bartlett and Orange County Public Works cordially invite you to the La Pata Gap Connector Ribbon Cutting Celebration!


April 19, 2016 
La Pata Extension Project Update

News ImageThe La Pata Avenue Extension Project Team is proud to announce the project's Two-Year Construction Milestone!


April 19, 2016 
County's La Pata Ave Extension nearly 90% complete

News ImageOC Public Works reaches 2-year construction milestone as extension portion of the major road project is expected to be completed in August 2016. View update for details and to see the project's photo gallery.


February 1, 2016 
A "Peek at La Pata" hike led by the City of San Clemente and OC Public Works

News Image

In collaboration with OC Public Works, the City of San Clemente hosted a "Peek at La Pata" hike for interested residents on Saturday, January 23. The fun event attracted around 250 people and gave participants an up-close look at the La Pata Avenue Extension Project.

To view the hike, the City of San Clemente created a video capturing the event.


January 19, 2016 
Join the City for "A Peek at La Pata" Hike

News ImageGet an up-close look of the La Pata extension project progress from City and OC Public Works representatives.


November 2, 2015 
La Pata Extension Project Update

News ImageThe contractor will resume importing dirt for grading of the La Pata Extension Project which will connect the communities of San Juan Capistrano and San Clemente.


September 29, 2015 
NOTICE OF NEIGHBORHOOD WORKSHOP

News ImageThis is a City meeting about City improvements to the existing Camino del Rio. This meeting is not regarding the La Pata Extension Project.

The City will be holding this Neighborhood Workshop to receive public input to help define project goals and objectives, performance measures, and design strategies to achieve project goals for Camino Del Rio. The project background, schedule, and purpose will be presented. Residents and all interested parties are invited to attend and provide input into the project.


August 14, 2015 
La Pata Extension Project Update

News ImageThe La Pata Avenue Extension Project Team is proud to announce that refuse removal was completed on August 3, 2015! Approximately 800,000 cubic yards of refuse were excavated and relocated to another location within Prima Deshecha Landfill to facilitate the construction of this project. The project will improve regional mobility for commuters by providing a direct connection between the communities of San Juan Capistrano and San Clemente.


May 4, 2015 
La Pata Extension Project Update

News ImageBeginning on or after May 6, 2015 for approximately 5 days from 8pm to 5am, the contractor will begin importing dirt at night for grading of the La Pata Extension Project which will connect the communities of San Juan Capistrano and San Clemente.


April 23, 2015 
La Pata Extension Project Update

News ImageThe La Pata Avenue Extension Project Team is proud to announce the project’s One-Year Construction Milestone!


February 17, 2015 
La Pata Extension Project Uncovers Marine Life Fossils Dating Back Millions of Years

News ImageExtremely rare discovery of leatherback sea turtle fossils is only the third known location in the state. See television news coverage here: NBC 4 and KCAL 9/CBS 2.


February 10, 2015 
La Pata Extension Project Update

News ImageImport has been progressing smoothly for grading of the La Pata Extension Project which will connect the communities of San Juan Capistrano and San Clemente. In an effort to complete construction-related activities at an earlier date and reduce potential impacts for commuters, the contractor import hours have adjusted.


December 18, 2014 
La Pata Extension Project Update

News ImageThe contractor will begin importing dirt for grading of the La Pata Extension Project which will connect the communities of San Juan Capistrano and San Clemente.


November 6, 2014 
La Pata Extension Project Update

News ImageConstruction moving Forward. The contractor has made significant progress with the completion of 95% refuse removal at the Prima Deshecha Landfill and 30% of earthwork.


August 1, 2014 
La Pata Extension Project Update

News ImageConstruction of the La Pata Extension Project continues on the La Pata Gap Connector Phase. Clearing and grubbing has been completed and the contractor has completed 50% of refuse removal at the Prima Deshecha Landfill to make room for the new La Pata Avenue. Construction activities for the next six months will include earthwork, drainage improvements, refuse removal, utility relocations, and bridge construction.


July 30, 2014 
Updated Trail Closure Map

News ImageThe trail closure map for the La Pata Extension Project has been updated. The Prima Deshecha Trail will be closed until Fall 2016 at the locations shown on the map. The Forster Ridgeline Trail will remain open to the public. We appreciate your patience and support during construction of the Project.


June 5, 2014 
La Pata Gap Connector Update

News ImageConstruction continues for the La Pata Gap Connector Phase. This phase is expected to be completed in Fall 2016. Below are the details of the project’s construction activities for the upcoming weeks:

REPORTING PERIOD: Monday, June 2 to Friday, June 20, 2014, weekdays, 7 a.m. to 5:30 p.m.


May 5, 2014 
La Pata Gap Connector Phase Begins!

News ImageThe contractor of La Pata Extension Project has begun the construction of the La Pata Gap Connector Phase that will extend the existing La Pata Avenue just south of Vista Montana to Calle Saluda with four new travel lanes for approximately 2.27 miles. The phase is expected to be completed in Fall 2016. Below are the details of the project’s construction activities for the upcoming weeks:
WHEN: May 1 to May 16, 2014, weekdays, 7 a.m. to 5:30 p.m.


April 22, 2014 
Prima Deshecha Landfill Update

News ImageDear Neighbor,
As many of you will recall, OC Waste & Recycling had the opportunity to meet with Rancho San Juan residents on the evening of February 20, 2014. During this meeting, OC Waste & Recycling staff discussed the many best management practices that were being implemented and considered to address any inconvenience you may experience from our landfill operations. We realize that not all residents were able to attend that meeting and invite each of you to view the presentation provided that evening on the Prima Deshecha Landfill webpage located at http://oclandfills.com/landfill/active/deshecha.


April 4, 2014 
LA PATA EXTENSION PROJECT – Transportation Relief Coming to Orange County

News ImageSOUTH ORANGE COUNTY – OC Public Works broke ground today on the La Pata Extension Project; the project will increase Orange County’s regional mobility by providing a north-south alternative to Interstate 5 and eliminating the existing gap between Ortega Highway to the north and Avenida Vista Hermosa to the south.


March 25, 2014 
Trail Closures

News ImageBeginning Spring of 2014, the County of Orange Public Works Department will break ground on the La Pata Avenue Gap Closure and Camino Del Rio Extension Project. The Initial Phase of the project is expected to be completed by Fall 2016. During this period, the Prima Deshecha and Forster Ridgeline Trails will be closed at the locations shown on the map. We appreciate your patience and support during construction of the Project.


February 24, 2014 
La Pata Community Letter

News ImageIn Spring 2014, the County of Orange Public Works Department will break ground on an important transportation project - the La Pata Avenue Gap Closure and Camino Del Rio Extension Project (Project). The Project will improve South County mobility and reduce local traffic congestion by providing a north/south alternative for daily commuters and will ultimately provide an alternative access route in the event of an emergency, and will benefit the community by providing improved access to schools, residences, commercial areas, and recreational amenities.


November 19, 2013 
Orange County Board of Supervisors Meeting Item S22A

Orange County Board of Supervisors Meeting Item S22A.
S22A. OC Public Works - Consider whether to award contract to Papich Construction Company Board rejected all bids and authorize the Project.


February 15, 2012 
La Pata Gap Closure and Camino Del Rio Extension Update

City Council City of San Clemente...


May 24, 2011 
Orange Board of Supervisors/Staff Report-La Pata/del Rio Final EIR

Orange Board of Supervisors/Staff Report-La Pata/del Rio Final EIR...


April 27, 2011 
Orange County Planning Commission/Staff Report-La Pata/del Rio Final EIR

Orange County Planning Commission/Staff Report-La Pata/del Rio Final EIR...


April 21, 2011 
La Pata / Del Rio - Final EIR Press Release

SANTA ANA - On April 27, 2011, the Orange County Planning Commission will consider the final Environmental Impact Report (EIR) for the proposed La Pata Gap Closure and Camino del Rio Extension...


April 18, 2011 
La Pata / Del Rio - Final EIR Stakeholder letter

I am writing to provide you with an update on the status of the proposed La Pata Gap Closure and Camino del Rio Extension to complete the Environmental Impact Report (EIR) and establish a final road aligment...


April 6, 2011 
La Pata/del Rio-Final EIR/Notice of Availability

This notice is intended to inform interested parties of the availability of the Final Environmental Impact Report (Final EIR) for the proposed La Pata Gap Closure and Camino Del Rio Extension Project (proposed project)...


November 3, 2010 
La Pata Draft EIR Release

La Pata Draft EIR Release...


October 27, 2010 
Draft Environmental Impact Report Review and Public Meeting in November Regarding Proposed La Pata Gap Closure, Camino del Rio Extension

A Draft Environmental Impact Report (DEIR) for the proposed La Pata Gap Closure and Camino del Rio Extension is available for a 45-day public review period on November 3...


April 12, 2010 
Environmental Process Continues for Proposed La Pata Gap Closure Project

SANTA ANA--Work leading to an environmental impact report (EIR) for a project that will widen a portion of La Pata Avenue continues with a Draft EIR expected this summer...


December 4, 2009 
La Pata/Del Rio Letter to Residents Within Quarter Mile of Project

We are writing to inform you about the status of the proposed La Pata Gap Closure and Camino Del Rio Extension in your community and the renewed efforts...


December 2, 2009 
La Pata Avenue Gap CLosure and Camino Del Rio Edxtension

Provide the public with an opportunity to participate in the environmental review process...


November 20, 2009 
Notice of Public Meeting on December 2, 2009 on the proposed La Pata Gap Closure & Camino Del Rio Extension Project

On December 2, 2009 the County of Orange will host a public meeting to solicit community input on the scope of the Environmental Impact Report (EIR) for the proposed La Pata Gap Closure & Camino Del Rio Extension Project...


November 16, 2009 
Environmental Process Moves Ahead for La Pata Gap Closure and Extension of Camino Del Rio

The County of Orange is moving ahead with steps leading to an environmental impact report (EIR) for a project that will improve traffic congestion, minimize environmental impacts and maintain and improve south Orange County's quality of life...


November 11, 2009 
La Pata Gap Closure and Camino Del Rio Extension Fact Sheet 1

The County of Orange is conducting preliminary alignment and environmental studies for the La Pata Closure and Camino Del Rio Extension projects...